CITIZEN’S CHARTER

PREPARATION OF PROGRAM OF WORKS (BARANGAY FUNDED PROJECTS/MOOE AND OTHER OFFICE REQUESTS)

ABOUT THE SERVICE:

Preparation of plans and designs for proposed barangay funded infrastructure projects. Schedule of Availability of Service: Monday – Friday: 8:00 am to 5:00pm


OFFICE DIVISION:

City Engineering Office

TYPE OF TRANSACTION:

G2C - Government to Customer

Classification:

Highly Technical

WHO MAY AVAIL:

Government to Client - Barangays


CHECKLIST OF REQUIREMENTS:

CHECKLIST OF REQUIREMENTS WHERE TO SECURE
(2 copies) Letter Request for Program of Works Request. End User (Barangay Officials – Duly Authorized) 
(1) Original Plans from City Architect’s Office.  City Architect’s Office

 

CLIENT STEPS:

CLIENT STEPS DEPARTMENT ACTIONS FEES TO BE PAID PROCESSING TIME PERSON RESPONSIBLE
1. Submit all the necessary documents needed for the 
preparation of Program of Works (Request Letter and Plans)  
1.1 Receive and review the submitted documents.   None 3 minutes  Aveihgail L. Argete
Administrative 
Assistant II 
City Engineering Office 
  1.2 Forward the same documents to the engineer in charged. None 3 minutes  Aveihgail L. Argete
Administrative Assistant II 
City Engineering Office
  1.3 Preparation of Program of Works None 3 working days John Dave C. Constantino
Engineer I
City Engineering Office
or
Glenbert R. Potestades
Engineer II
City Engineering Office
or
Edgardo A. Rubio
Construction and Maintenance 
City Engineering Office
  1.4 The Assistant City Engineer will check and review the prepared Program of Works and Plan and endorse it to the City Engineer for signature. None 1 working day Sergia A. Dapito
Assistant City Engineer
City Engineering Office
  1.5 Prepared program of works for approval and the City Engineer will affix signature None 1 working day Christian T. Tamaño
City Engineer
City Engineering Office
2. Receives the complete set of Program of Works and Plan. 21. Record and release the same documents. None 3 minutes Aveihgail L. Argete
Administrative Assistant II
City Engineering Office
  TOTAL: None 5 days and 9 minutes  

 

Scroll to Top