ISSUANCE OF DEVELOPMENT/MEMORIAL PERMIT
ABOUT THE SERVICE:
A Development Permit shall be secured prior to the development of any area or portion of land prior to subdivision thereof within the territorial jurisdiction of the City of Tayabas.
OFFICE DIVISION:
Office of the Building Official
TYPE OF TRANSACTION:
G2C - Government to Customer, G2B - Government to Business, G2G - Government to Government
Classification:
Highly Technical
WHO MAY AVAIL:
Any person, firm or corporation, including any agency or instrumentality of the government who wants to subdivide a portion/area of land within the jurisdiction of the City of Tayabas
CHECKLIST OF REQUIREMENTS:
| CHECKLIST OF REQUIREMENTS | WHERE TO SECURE |
| FOR TYPICAL SUBDIVISION | |
|
Applicant |
|
Applicant |
|
Applicant |
|
Applicant |
|
Applicant |
|
Applicant |
|
Applicant |
|
Applicant |
|
Applicant |
|
Applicant |
|
Applicant |
|
Applicant |
|
Applicant |
|
Applicant |
|
Applicant |
|
Applicant |
|
Applicant |
|
Applicant |
|
Applicant |
|
Applicant |
|
Applicant |
: Development Permit - qualified for multi-stage processing
CLIENT STEPS:
| CLIENT STEPS | DEPARTMENT ACTIONS | FEES TO BE PAID | PROCESSING TIME | PERSON RESPONSIBLE |
| 1 Preparation & Submission of Documents | ||||
|
1.1.1 Visit the office (Window) for the hard copy of forms and checklist
|
1.1 Give set of documents for construction permit application & assist client | None |
5 minutes
|
Allison R. Cuevas |
| 1.2 Prepare the necessary documents, sort and arrange according to checklist and secured each set with a staple or binder clip | ||||
| 1.3 Submission documents |
1.3.1 Checking the completeness of documents.
|
None
None
None
|
20 minutes
5 minutes
5 minutes |
Allison R. Cuevas
Allison R. Cuevas
Allison R. Cuevas |
|
Internal Process
|
None | 5 minutes | Allison R. Cuevas Engineering Aide Building Official |
|
| Internal Process 1.3.3. Site Verification |
None | 1 day |
Engr. Zaldy R. Cademia Ar. Elizabeth D. Enriquez Ar. Mark Anthony M. Barquilla Engr. Gilbert T. Oabel Engr. Ara Tabitha A. Quevada Engr. Francis S. Pacaigue |
|
|
Internal Process
|
None
None
None
None
None |
19 days (in total) |
Ar. Elizabeth D. Enriquez
Ar. Mark Anthony M. Barquilla
Engr. Zaldy R. Cademia
Engr. Ara Tabitha A. Quevada
Engr. Gilbert T. Oabel |
|
|
Internal Process 1.3.5.2 If the application is not compliant,
|
None
None
None
|
1 hour
5 minutes
5 minutes
|
Engr. Francis S. Pacaigue
Allison R. Cuevas
Allison R. Cuevas
|
|
| 1.4 Claim Transmittal Sheet, pull out plans/documents (if necessary) and sign the Transmittal sheet acknowledging receipt (Refer with your design professionals for your necessary corrections as indicated on the copy of Transmittal given) |
1.4 Assist Client in documents/permit forms/plans pulled-out for compliance |
None |
10 minutes (varies from |
Allison R. Cuevas |
| 1.5 Submit the corrected documents |
1.5.1 Check if corrections have been done.
1.5.3.1 Site Development/Topographical Map, Model Houses and other facilities
|
None
None
None
None
None
None
None
None
|
10 minutes (varies from
5 minutes (varies from
3 days – in total (varies
5 minutes
5 minutes
|
Allison R. Cuevas
Allison R. Cuevas
Ar. Elizabeth D. Enriquez
Ar. Mark Anthony M. Barquilla
Engr. Zaldy R. Cademia
Engr. Ara Tabitha A. Quevada
Engr. Gilbert T. Oabel
Allison R. Cuevas
Allison R. Cuevas
|
| 2 Payment | ||||
|
2.1 Pay the Cashier (Window 4)
|
2.1.1 Issue Official Receipt
2.1.2 Encode & Assign Development Permit Number 2.1.3 Print Certificate of Occupancy 2.1.4 Signing as approval of Development |
Refer to the schedule fees (National Building
None
None
None
|
5 minutes
15 minutes
5 minutes
10 minutes
|
Treasurer’s
Engr. Maria Leila P. Jarena
Engr. Francis S. Pacaigue |
| 3 Releasing of Approved Final Permit |
||||
|
3.1 Claiming of Approved Development Permit
|
3.1.Releasing of documents
|
None
None |
10 minutes (in total) |
Allison R. Cuevas
Allison R. Cuevas |
|
3.3 Bring the Approved Development Permit Form to OCPDC-Zoning & CDRRMO |
|
|
|
|
|
3.4 Bring copy of signed Development Permit |
3.3 Received copy of signed Development Permit |
None |
2 minutes |
Allison R. Cuevas |
|
|
TOTAL |
Refer to the schedule fees (National Building |
For Highly Technical Transactions: |
|
|
|
|
END OF TRANSACTION |
|
|