Issuance of other Permits - Development Permit

FRONTLINE SERVICE: Issuance of other Permits – Development Permit

SCHEDULE OF AVAILABILITY OF SERVICE: Every day except weekends & holidays. 10am to 5pm

WHO MAY AVAIL OF THE SERVICE: Applicants of subdivision development projects (new and expansion)


DOCUMENTS NEEDED: 

• Application Form for Development Permit (notarized)

• Four (4) original copies of Topographic Map of Site signed & sealed by Geodetic Engineer

• Four (4) original copies of Site Development Plan signed & sealed by licensed Civil Engr/ Architect

• Four (4) copies of Road (geometric structural) Design signed & sealed by civil Engr.

• Four (4) copies of Storm Drainage and Sewer system signed & sealed by Sanitary Engr/ Civil Engr

• Four (4) copies of Water System layout and details signed & sealed by Sanitary Engineer/ Civil engr

• Four (4) copies of Site Grading Plan signed by Civil Engr.

• Four (4) copies of Project Feasibility Study signed by Civil Engr.

• Four (4) copies of Electrical Distribution System signed by PEE

• Specifications, Bill of Materials, Cost Estimates signed & sealed by Civil Engineer

• Certification from MERALCO

• Certification from Prime Water (If not, a plan of overhead water tank together with NWRB clearance)

• Engineering Geological and Geohazard Assessment Report prepared by qualified geologist or engineer as required
under Administrative Order No. 2000-28 signed by the DENR Secretary Antonio H. Cerilles.

• Environment Compliance Certificate

• Certified True Copy of Lot title

• Tax Declaration and latest Tax Receipt (reproduced copy)

• Barangay Clearance

• PALC (Preliminary Approval & Locational Clearance)

FOR HOUSING CONSTRUCTION: 

• Four (4) sets of plans (Architectural, Sanitary, Electrical, Structural, Specs and Cost estimates) signed & sealed by
Professionals

• Sworn Statement notarized (Soundness of designs, specs and cost estimates.

OTHER REQUIREMENTS: 

• Secretary Certificate (if applicable)

• PTR/PRC of Professionals

• Valid IDs

PROCESSING OF DOCUMENTS: Every day except weekends & Holidays 8am to 5pm

FEES: Based on the National Building Code of the Philippines PD 1096

PROCESSING TIME: Complex – 14 working days


HOW TO AVAIL OF THE SERVICE:

STEPPROCEDURESACTION OFFICERPERSON IN CHARGEDURATION OF ACTIVITYFORM
1Submission of Documentary
Requirement
Receiving, Initial Checking &
Encoding
A.Cuevas20minutesCustomer Service
Feedback Form:
Form 1 – end of
transaction feedback form
available in the offices
Form 2 – random survey/
walk-in complaint form
available in PACO
2 Evaluation
(Line & Grade,
Architectural, Structural,
Electrical, Sanitary/
Plumbing)
E. Enriquez/
G. Oabel/
A. Quevada/
F. Pacaigue

Complex – 5 hrs.

NOTE : time is applicable for
each evaluator for each
section

Total evaluation time :
7 working days

Development Permit
Forms & Plans
3 Endorsement to OSTM. Rabina/
F. Pacaigue
 Demolition Permit
Forms & Plans

 

Endorsement Letter

4b. PaymentIf complied with OST &
OBO:
a.Assessment
c.Recording
d.Releasing
F. Pacaigue/
M. Jarena/
A.Cuevas
10 minutes
10 minutes
20 minutes
10 minutes
Order of Payment
Official Receipt
Development Permit
Certificate
Customer Service
Feedback Form:
Form 1 – end of
transaction feedback
form available in the
offices
Form 2 – random
survey/ walk-in
complaint form
END OF TRANSACTION